Suzuki Motor Corporation has been suspended operations except completion of the vehicles at the assembly lines.
We will suspend operations at the automobile assembly plants as some necessary parts supplied from the factories at the disaster area are still difficult to be procured stably. However, the other plants such as the engine assembling plants will operate on 24 and 25 March (day-shift only) while we use stock components. Operation after 28 will be decided after we assess the situation.
24 March | 25 March | ||
Kosai Plant | Passenger car assembling | Suspend | Suspend |
Iwata Plant | Multi-purpose vehicle and commercial vehicle assembling | Suspend | Suspend |
Sagara Plant | Passenger car assembling | Suspend | Suspend |
Automobile engines assembling | Operate | Operate | |
Toyokawa Plant | Motorcycles assembling | Operate | Operate |
Outboard motor assembling | Operate | Operate | |
Takatsuka Plant | Motorcycle engines assembling and machining | Operate | Operate |
Osuka Plant | Foundry | Operate | Operate |
All plants will be closed on 26 and 27 March for the holidays.