Global News

23 March 2011

Suzuki plants operations (Report #4)

Suzuki Motor Corporation has been suspended operations except completion of the vehicles at the assembly lines.

We will suspend operations at the automobile assembly plants as some necessary parts supplied from the factories at the disaster area are still difficult to be procured stably. However, the other plants such as the engine assembling plants will operate on 24 and 25 March (day-shift only) while we use stock components. Operation after 28 will be decided after we assess the situation.

  24 March 25 March
Kosai Plant Passenger car assembling Suspend Suspend
Iwata Plant Multi-purpose vehicle and commercial vehicle assembling Suspend Suspend
Sagara Plant Passenger car assembling Suspend Suspend
Automobile engines assembling Operate Operate
Toyokawa Plant Motorcycles assembling Operate Operate
Outboard motor assembling Operate Operate
Takatsuka Plant Motorcycle engines assembling and machining Operate Operate
Osuka Plant Foundry Operate Operate

All plants will be closed on 26 and 27 March for the holidays.